Progress Update, Week of June 2nd, 2025

During the week of June 2, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued near 9th Street. Grout was placed. Site restoration was performed at completed sections.

Bulkhead installation continued at the 7th Street Turning Basin. Tiebacks were installed. Grout was placed.

Bulkhead installation continued near Bush Street. Tiebacks were installed.

Bulkhead installation continued at the 6th Street Turning Basin. Sheet piles were installed.

Photos of construction activities are provided below.

Tieback installation near 9th Street.
Sheet pile installation at the 6th Street Turning Basin.