Progress Update, Week of June 30th, 2025

During the week of June 30, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued near 9th Street. Grout was placed. Site restoration was performed at completed sections.

Bulkhead installation continued at the 7th Street Turning Basin. Tiebacks were installed. Grout was placed.

Bulkhead installation continued near 3rd Street. Tiebacks were installed.

Bulkhead installation continued at the 6th Street Turning Basin. Sheet piles were installed. Sealant was placed.

Photos of construction activities are provided below.

Obstruction removal installation at the 6th Street Turning Basin.
Sheet pile installation at the 6th Street Turning Basin.