Skip to content

Progress Update, Week of June 5th, 2023

During the week of June 5, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material placement began between Union Street and Carroll Street.

Photos of construction activities are provided below.

Capping equipment staged between Union Street and Carroll Street.
Capping material placement between the Union Street Bridge abutments.