During the week of June 9, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.

Bulkhead installation continued near 9th Street. Grout was placed. Site restoration was performed at completed sections.

Bulkhead installation continued at the 7th Street Turning Basin. Tiebacks were installed.

Bulkhead installation continued near Bush Street. Tiebacks were installed.

Bulkhead installation continued at the 6th Street Turning Basin. Sheet piles were installed.

Photos of construction activities are provided below.

Preparing for sheet pile installation at the 6th Street Turning Basin.
Backfilled test pits at the 6th Street Turning Basin.