During the week of March 10, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.
Bulkhead installation continued at the 4th Street Turning Basin. Tieback installation continued. Grout was placed. Site restoration was performed at completed bulkheads.
Bulkhead installation continued at the 7th Street Turning Basin. Sheet pile installation continued. Sealant was placed.
Bulkhead installation continued near 9th Street. Tieback installation continued. Grout was placed.
Bulkhead installation began near 3rd Street. Sheet piles were installed.
Photos of construction activities are provided below.

