Progress Update, Week of March 14th, 2022

During the week of March 14 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Union Street Bridge.

Remedial construction activities continued at the Union Street Bridge. Mechanical restraints were installed in preparation for additional upcoming work. The Union Street Bridge will be intermittently closed to all traffic during daytime hours, 9am – 2pm, for up to five days a week. For more information read the latest public notices on gowanussuperfund.com.

At Degraw Street the GRT continued tieback installation. Tieback anchors were locked off. Tieback rods were trimmed as needed and sealed. A partial street closure will remain in place on Degraw Street between Bond Street and the Gowanus Canal while this work is ongoing.

Photos of construction activities are provided below.

Continued ISS near the Union Street Bridge.
Tieback installation in progress at Degraw Street.