Progress Update, Week of March 21st, 2022

During the week of March 21 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Union Street Bridge.

At Degraw Street the tieback installations were completed. Tieback equipment was demobilized. Workers began cutting drainage holes, installing a filtration system, and restoring the roadway. A partial street closure will remain in place on Degraw Street between Bond Street and the Gowanus Canal while this work is ongoing.

Crews began preparing the staging area for upcoming phase 2 dredging.

Photos of construction activities are provided below.

ISS in progress.
Demobilizing tieback equipment.
Installing bridge restraints at the Union Street Bridge.