During the week of March 28 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS). The ISS work barges were relocated to conduct ISS near the Carroll Street Bridge.
Closure sheet piles were installed at the Carroll Street Bridge.
At Degraw Street workers continued cutting drainage holes, installing a filtration system, and restoring the roadway. A partial street closure will remain in place on Degraw Street between Bond Street and the Gowanus Canal while this work is ongoing.
Crews began preparing the staging area for upcoming phase 2 dredging.