Skip to content

Progress Update, Week of March 28th, 2022

During the week of March 28 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS). The ISS work barges were relocated to conduct ISS near the Carroll Street Bridge.

Closure sheet piles were installed at the Carroll Street Bridge.

At Degraw Street workers continued cutting drainage holes, installing a filtration system, and restoring the roadway. A partial street closure will remain in place on Degraw Street between Bond Street and the Gowanus Canal while this work is ongoing.

Crews began preparing the staging area for upcoming phase 2 dredging. 

Photos of construction activities are provided below.

ISS in progress south of the Carroll Street Bridge.
ISS in progress north of the Carroll Street Bridge.
Closure sheet pile installation near the Carroll Street Bridge.
Updated Signage at Carroll Street.
ISS in progress south of the Carroll Street Bridge.