Progress Update, Week of March 6th, 2023

During the week of March 6, the Gowanus Remediation Team (GRT) continued the Demonstration Test for the RTA 1 Capping Operation. Capping material was placed and leveled. Surveying was conducted to review the newly placed cap.

Photos of construction activities are provided below.

Capping material placement in progress.
Continued capping material placement.