Progress Update, Week of May 23th, 2022

During the week of May 23 the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) north of Union Street.

Monopile installation commenced at the north side of the Union Street Bridge.

The timber dolphins at the Third Street Bridge were removed.

Work on the drainage and filtration systems at the Degraw Street bulkhead continued.

Photos of construction activities are provided below.

ISS In progress north of Union Street.
Monopile Installation at the Union Street Bridge
Timber Dolphin removal at the Third Street Bridge.