During the week of May 25, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.
Bulkhead installation continued at the 6th Street Turning Basin. Installed sheet piles were backfilled. Drain outlets were installed.
Bulkhead installation continued near Bond Street. Drain pipes were installed.
Bulkhead installation continued near 9th Street. Drain outlet covers were installed.
Bulkhead installation continued at the 7th Street Turning Basin. Tiebacks were installed. Installed sheet piles were backfilled.
Photos of construction activities are provided below.

