Progress Update, Week of May 9th, 2022

During the week of May 2 the Gowanus Remediation Team (GRT) completed Phase 2 dredging near the Union Street Bridge. Sediment was raked following the completion of dredging activities.

At Degraw Street workers continued cutting drainage holes, installing a filtration system, and restoring the roadway. A closure sheet was installed and sealant was applied at the new bulkhead. A partial street closure will remain in place on Degraw Street between Bond Street and the Gowanus Canal while this work is ongoing.

Photos of construction activities are provided below.

Dredging north of the Union Street bridge.
Raking sediment north of the Union Street Bridge.
Installing closure sheet at the Degraw Street bulkhead.