During the week of November 11, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System operations.
Bulkhead installation continued at the 4th Street Turning Basin. Tieback installation continued.
Bulkhead installation continued at the 7th Street Turning Basin. Equipment was mobilized for additional sheet pile installation.
Photos of construction activities are provided below.