During the week of November 18, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System operations.

Bulkhead installation continued at the 4th Street Turning Basin. Tieback installation continued.

Bulkhead installation continued at the 7th Street Turning Basin. Recently installed sheet piles were backfilled. Sheet pile installation continued.

Photos of construction activities are provided below.

Sheet pile installation in progress at the 7th Street Basin.
Tie back installation in progress at the 4th Street Basin.