Progress Update, Week of November 4th, 2024

During the week of November 4, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System operations.

Bulkhead installation continued at the 4th Street Turning Basin. Backfilling was completed. Tieback installation began.

Bulkhead installation continued at the 7th Street Turning Basin. One sheet pile wall was completed. The site was cleared for additional sheet pile installation.

Photos of construction activities are provided below.

Sheet pile installation in progress at the 7th Street Basin.
Continued sheet pile installation in progress at the 7th Street Basin.