Skip to content

Progress Update, Week of November 14th, 2022

During the week of November 14, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging north of Union Street.

Water storage tanks at the staging area were power washed.

Testing was completed for the new power and control cables at the Union Street Bridge. The work site was cleaned. Demobilization of the temporary cable system began.

Mobilization continued at the new GRT staging area. Demobilization continued at the current GRT staging area.

Photos of construction activities are provided below.

Dredging in progress north of Union Street.
Continued dredging in progress north of Union Street.