Skip to content

Progress Update, Week of November 8, 2021

During the week of November 8, the Gowanus Remediation Team (GRT) continued mobilizing equipment and materials in preparation for sheet pile bulkhead installation work near the head of the canal.

Pipe pile cutting continued at the Carroll Street Bridge.  Pipe piles that were installed within the navigational channel are being cut to an appropriate height.

Analysis of the In-Situ Stabilization (ISS) demonstration test results is ongoing.

Photos of construction activities are provided below.

Lowering a cutting tool into a pipe pile at the Carroll Street Bridge.

Mobilizing equipment and materials for bulkhead installation.