Skip to content

Progress Update, Week of October 10th, 2022

During the week of October 10, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging between Carroll Street and Union Street.

Power and control cable installation and testing continued at the Union Street Bridge. Steel grating platform installation continued.

Cap plate installation began at the Degraw Street bulkhead.

An anchor plate was installed at the 1st Street bulkhead.

Mobilization continued at the new GRT staging area.

Photos of construction activities are provided below.

Dredging north of Carroll Street.
Continued dredging north of Carroll Street.