During the week of October 14, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Installation operations.

Bulkhead installation continued near 6th Street. Preparations were made for upcoming tieback installations. Newly installed sheet piles were surveyed.

Bulkhead installation continued near 3rd Street. Sheet piles were installed. Newly installed sheet piles were surveyed. Existing drainpipes were extended.

Preparations were made for upcoming bulkhead installation near 2nd Avenue.

Mobilization began at the staging area for tieback operations. Assembly of a temporary floating platform began.

Photos of construction activities are provided below.

Sheet piles installation in progress near 3rd Street.
Measuring final bulkhead elevation near 3rd Street.