During the week of October 16, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed and graded north of Union Street. The excavator was transported south of Carroll Street for additional material placement.

Photos of construction activities are provided below.

Capping material placement in progress.
Continued capping material placement.