Skip to content

Progress Update, Week of October 17th, 2022

During the week of October 17, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging. Sediment was dredged between the Union Street Bridge abutments. A cleanup pass was conducted and dredging was completed between Carroll Street and Union Street.

Power and control cable installation and testing was completed at the Union Street Bridge. Steel grating platform installation continued.

Cap plate installation was completed at the Degraw Street bulkhead.

Mobilization continued at the new GRT staging area.

Photos of construction activities are provided below.

Dredging in progress south of Union Street.
Dredging in progress between the Union Street bridge abutments.
Cap plate installed at the Degraw street bulkhead.