Progress Update, Week of October 24th, 2022

During the week of October 24, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging north of Union Street.

Steel grating platform installation was completed at the Union Street Bridge.

Mobilization continued at the new GRT staging area.

Photos of construction activities are provided below.

Dredging in progress north of Union Street.
Continued dredging north of Union Street.