During the week of October 27, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Support System installation operations.
Bulkhead installation continued near 9th Street. Grout was placed. Bearing plates were sealed. Sheet piles were installed and cut to grade. Drain outlets were installed. Backfill was graded. Site restoration continued.
Bulkhead installation continued near 3rd Street. Tiebacks were installed. Grout was placed. Drain outlets were installed.
Bulkhead installation continued at the 7th Street Turning Basin. Drain outlets were installed.
Bulkhead installation continued at the 6th Street Turning Basin. Tiebacks were installed. Grout was placed.
Bulkhead installation began near 12th Street. Sheet piles were installed.
Photos of construction activities are provided below.

