During the week of October 28, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Installation operations.
Backfilling continued at the newly installed bulkheads near 3rd Street. Preparations were made for upcoming tieback installations.
Bulkhead installation began near 2nd Avenue. Sheet piles were installed.
Assembly of a temporary floating platform for the tieback operation at the staging area was completed.
Photos of construction activities are provided below.