During the week of October 3, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging between Carroll Street and Union Street.
Power and control cable installation and testing continued at the Union Street Bridge. Steel grating platform installation continued.
Mobilization continued at the new GRT staging area.
Photos of construction activities are provided below.