Progress Update, Week of September 12th, 2022

During the week of September 12, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging between 3rd Street and Carroll Street.

Cables were prepared for installation and pull boxes were installed at the Union Street Bridge.

Samples collection was completed at the eastern Union Street Bridge pier.

Sediment was removed, sealant was placed, and sheet piles were cut to the correct height near the Carroll Street Bridge.

Photos of construction activities are provided below.

Phase 3 Dredging in progress.
Clearing sheet pile “bellies” with sheet pile bucket.
Sheet pile bucket excavator attachment.