Progress Update, Week of September 16th, 2024

During the week of September 16, the Gowanus Remediation Team (GRT) continued RTA 2 Bulkhead Installation operations.

Bulkhead installation continued near 6th Street. Sheet pile installation continued. Monitoring equipment was installed.

Access dredging was completed and the associated equipment was demobilized.

Photos of construction activities are provided below.

Sheet pile installation in progress with Silent Piler near 6th Street.
Aerial view of 6th Street work zone.