Skip to content

Progress Update, Week of September 26th, 2022

During the week of September 26, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging between Carroll Street and Union Street.

Power and control cable installation continued at the Union Street Bridge. Newly installed cables were tested to ensure performance. Steel grating platform installation commenced.

Sheet pile bulkheads were cut to grade, sediment was removed, and sealant was placed near Carroll Street.

Drain holes were cut in sheet pile bulkheads and the street was paved at Degraw Street.

Mobilization began for the new GRT staging area at the intersection of Smith Street and Bay Street.

Photos of construction activities are provided below.

Phase 3 Dredging north of the Carroll Street Bridge.
Continued Phase 3 Dredging north of the Carroll Street Bridge.
Newly paved roadway at Degraw Street.