Progress Update, Week of September 28th, 2026

The Gowanus Remediation Team (GRT) has substantially completed its installation of Bulkhead Support Systems within Remediation Target Area 2 (RTA 2).

The next construction activity will be Early Phase 2 Dredging for RTA 2. More information about the logistics and scheduling of this work will be published on www.GowanusSuperfund.com as it becomes available.

During this interim period between phases of work the GRT may temporarily reduce the frequency of Progress Updates and Water Quality Monitoring Reports. These reports will be published on an as-needed basis until regular GRT construction activities resume. The Community Air Monitoring Program will be limited to the project staging area while there is no active work happening in the Canal.

Now Live: The Gowanus Transformation Through Generations Storymap