Progress Update, Week of September 4th, 2023

During the week of September 4, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed between Carroll Street and 3rd Street.

Equipment and materials were staged for the upcoming transition from capping with the low velocity spreader to excavator-based material placement.

Photos of construction activities are provided below.

Capping material placement in progress between Carroll Street and Third Street.
Continued capping material staged for placement.