Cultural Resources Review Results #6, January 29, 2021

INTRODUCTION Dredged material is processed according to the Level 1 Archaeological Monitoring protocol outlined in the draft Cultural Resource Monitoring Plan (revised September 2020). This protocol calls for dredged soft sediments to be [...]

January 29th, 2021|

Cultural Resources Review Results #5, January 22, 2021

INTRODUCTION Dredged material is processed according to the Level 1 Archaeological Monitoring protocol outlined in the draft Cultural Resource Monitoring Plan (revised September 2020). This protocol calls for dredged soft sediments to be [...]

January 22nd, 2021|

Progress Report: December 23, 2020

On the morning of Monday, November 16, dredging of RTA1 commenced. The Gowanus Canal Superfund Project Team (“Project Team”) began removing debris and sediment from in front of the former First Street Turning Basin. (Click to read)

January 10th, 2021|

Cultural Resources Review Results #4, January 8, 2021

INTRODUCTION Dredged material is processed according to the Level 1 Archaeological Monitoring protocol outlined in the draft Cultural Resource Monitoring Plan (revised September 2020). This protocol calls for dredged soft sediments to be [...]

January 8th, 2021|