Cultural Resources Review Results #18, February 28, 2022
This memorandum presents the findings and recommendations of the archaeological documentation conducted at Turning Basin 1 (TB1) of the Gowanus Canal.
This memorandum presents the findings and recommendations of the archaeological documentation conducted at Turning Basin 1 (TB1) of the Gowanus Canal.
During the week of March 14 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Union Street Bridge.
During the week of March 7 the Gowanus Remediation Team (GRT) continued In-Situ Stabilization (ISS) near the Union Street Bridge.
During the week of February 28 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) south of the Union Street Bridge.
During the week of February 21 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) south of the Union Street Bridge.
During the week of February 14 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) north of the Carroll Street Bridge.
During the week of February 7 the Gowanus Remediation Team continued In-Situ Stabilization (ISS) north of the Carroll Street Bridge.
During the week of January 31, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade and north of the Carroll Street Bridge.
During the week of January 24, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
On 12/10/2021, the Gowanus Remediation Team was conducting In-Situ Stabilization (ISS) and during sampling activities associated with the ISS, a coin was discovered.