Progress Update, Week of August 9, 2021
During the week of August 9 the Gowanus Remediation Team continued pipe pile installation along the canal-facing sides of the Carroll Street bridge abutments.
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of August 9 the Gowanus Remediation Team continued pipe pile installation along the canal-facing sides of the Carroll Street bridge abutments.
During the week of August 2 the Gowanus Remediation Team continued pipe pile installation along the canal-facing sides of the Carroll Street bridge abutments.
During the week of July 26 the Gowanus Remediation Team completed repositioning the work barges around the Carroll Street bridge.
During the week of July 19 the Gowanus Remediation Team continued repositioning the work barges around the Carroll Street bridge.
During the week of June 14 the Gowanus Remediation Team continued with ongoing pile driving operations.