March 2016 Update
The design team is preparing for a debris removal pilot study, scheduled to begin in the summer of 2016. The pilot study will take place… Read More »March 2016 Update
The design team is preparing for a debris removal pilot study, scheduled to begin in the summer of 2016. The pilot study will take place… Read More »March 2016 Update
The Design Team and its contractors are currently engaged in several activities on the canal. These activities are part of their ongoing effort to further… Read More »March Update
During the last quarter of 2015, the Remedial Design team continued to collect field data and to submit reports to EPA presenting the findings from… Read More »February Update
The Design Team and its contractors are engaged in several activities on the canal. These activities are part of our ongoing effort to further study the canal and develop the remedial design.