Progress Update, Week of October 30th, 2023
During the week of October 30, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of October 30, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of October 23, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed south of Carroll Street.
During the week of October 16, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed and graded north of Union Street.
During the week of October 9, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of October 2, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of September 25, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement continued north of Union Street.
During the week of September 18, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement continued North of Union Street.
During the week of September 11, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement was completed using the low velocity spreader barge.
During the week of September 4, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed between Carroll Street and 3rd Street.
During the week of August 28, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed between Carroll Street and 3rd Street.