Progress Update, Week of September 19th, 2022
During the week of September 19, the Gowanus Remediation Team (GRT) completed Phase 3 Dredging between 3rd Street and Carroll Street.
During the week of September 19, the Gowanus Remediation Team (GRT) completed Phase 3 Dredging between 3rd Street and Carroll Street.
During the week of September 12, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging between 3rd Street and Carroll Street.
During the week of September 5, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging between 3rd Street and Carroll Street.
During the week of August 29, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging between 3rd Street and Carroll Street.
During the week of August 22, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging between 3rd Street and Carroll Street.
During the week of August 18, the Gowanus Remediation Team (GRT) completed mobilization and commenced with Phase 3 Dredging began between 3rd Street and Carroll Street.
During the week of August 8, the Gowanus Remediation Team (GRT) completed In Situ Stabilization (ISS) in Remediation Target Area 1 (RTA 1).
During the week of August 1, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) south of the Union Street Bridge.
During the week of July 25, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) south of the Union Street Bridge.
During the week of July 18, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) south of the Union Street Bridge.