Progress Update, Week of September 2nd, 2024
During the week of September 2, the Gowanus Remediation Team (GRT) continued the RTA 2 Access Dredging Operation to prepare locations of work for Bulkhead Installation.
During the week of September 2, the Gowanus Remediation Team (GRT) continued the RTA 2 Access Dredging Operation to prepare locations of work for Bulkhead Installation.
During the week of August 26, the Gowanus Remediation Team (GRT) continued the RTA 2 Access Dredging Operation in advance of upcoming Bulkhead Installation.
During the week of August 19, the Gowanus Remediation Team (GRT) continued the RTA 2 Access Dredging Operation.
During the week of August 12, the Gowanus Remediation Team (GRT) completed the RTA 1 Capping Operation. Supplemental dredging was completed. Monopile fenders were installed. Anchor points were removed. The main channel remediation for RTA 1 is now complete!
During the week of August 5, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Gravel placement near Douglass Street continued.
During the week of July 29, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Gravel placement near Douglass Street continued.
During the week of July 22, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of July 15, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of July 8, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of July 1, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.