Skip to content

Updates

Progress Update, Week of February 13th, 2023

  • by

During the week of February 13, the Gowanus Remediation Team (GRT) continued the Demonstration Test for the RTA 1 Capping Operation. Capping material was placed and graded.

Progress Update, Week of January 23rd, 2023

  • by

During the week of January 23, the Gowanus Remediation Team (GRT) began the. Material transportation piping installation was completed. Layering of material began within the test area. As the first phase of capping begins, this test will ensure that all equipment is calibrated correctly.

Progress Update, Week of January 16th, 2023

  • by

During the week of January 16, the Gowanus Remediation Team (GRT) continued mobilizing for the RTA 1 Capping Operation. The Capping Operation will place a layer of new material along the bed of the canal within RTA 1. Capping is expected to continue through Spring 2024.

Progress Update, Week of January 9th, 2023

  • by

During the week of January 9, the Gowanus Remediation Team (GRT) began mobilization for the RTA 1 Capping Operation. The Capping Operation will place a layer of new material along the bed of the canal within RTA 1. Capping is expected to continue through Spring 2024.

Progress Update, Week of January 2nd, 2023

  • by

During the week of January 2, the Gowanus Remediation Team (GRT) completed Phase 3 dredging between the Carroll Street Bridge abutments. All dredging has now been completed for RTA 1! Over the coming weeks the GRT will transition our operations to begin the RTA 1 Capping Operation.

Progress Update, Week of December 26th, 2022

  • by

During the week of December 26, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging near the Union Street Bridge and the Carroll Street Bridge abutments. Dredging also took place north of Union Street near the Flushing Tunnel.

Progress Update, Week of December 19th, 2022

  • by

During the week of December 19, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging near the Union Street Bridge and the Carroll Street Bridge abutments. Dredging also took place north of Union Street near the Flushing Tunnel. Divers were utilized for visual inspections.

Progress Update, Week of December 12th, 2022

  • by

During the week of December 12, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging near the Union Street Bridge and the Carroll Street Bridge abutments. Dredging also took place north of Union Street near the Flushing Tunnel.