Progress Update, Week of November 27th, 2023
During the week of November 27, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of November 27, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of November 20, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of November 13, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of November 6, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of October 30, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of October 23, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed south of Carroll Street.
During the week of October 16, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed and graded north of Union Street.
During the week of October 9, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of October 2, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
During the week of September 25, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement continued north of Union Street.