Progress Update, Week of January 17th, 2022
During the week of January 17, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of January 17, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of January 10, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of January 3, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) near the Bond Street Promenade.
During the week of December 27, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) along the Bond Street Promenade.
During the week of December 20, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) within RTA-1.
During the week of December 13, the Gowanus Remediation Team continued In-Situ Stabilization (ISS) within RTA-1.
During the week of December 6, the Gowanus Remediation Team continued sheet pile bulkhead installation at the head of the canal near Butler Street.
During the week of November 29, the Gowanus Remediation Team continued sheet pile bulkhead installation work near the head of the canal.
During the week of November 22, the Gowanus Remediation Team continued sheet pile bulkhead installation work near the head of the canal.
During the week of November 15, the Gowanus Remediation Team began installing sheet pile bulkheads near the head of the canal.