Progress Update, Week of August 8th, 2022
During the week of August 8, the Gowanus Remediation Team (GRT) completed In Situ Stabilization (ISS) in Remediation Target Area 1 (RTA 1).
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of August 8, the Gowanus Remediation Team (GRT) completed In Situ Stabilization (ISS) in Remediation Target Area 1 (RTA 1).
During the week of August 1, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) south of the Union Street Bridge.
During the week of July 25, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) south of the Union Street Bridge.
During the week of July 18, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) south of the Union Street Bridge.
During the week of July 11, the Gowanus Remediation Team (GRT) continued In Situ Stabilization (ISS) south of the Union Street Bridge.
To contact the Gowanus Remediation Team please email info@gowanussuperfund.com or call the hotline at (718) 569-5762.