Progress Update, Week of January 2nd, 2023
During the week of January 2, the Gowanus Remediation Team (GRT) completed Phase 3 dredging between the Carroll Street Bridge abutments. All dredging has now been completed for RTA 1! Over the coming weeks the GRT will transition our operations to begin the RTA 1 Capping Operation.
Sealant was placed at bulkheads and monopiles near the Union Street Bridge.
Mobilization continued at the new GRT staging area. Demobilization continued at the current GRT staging area.
Photos of construction activities are provided below.