2023 Progress Updates

Progress Update, Week of March 13th, 2023

During the week of March 13, the Gowanus Remediation Team (GRT) continued the Demonstration Test for the RTA 1 Capping Operation. Capping material was placed and surveying of the newly placed material was conducted.

Photos of construction activities are provided below.

Capping material placement in progress.
Surveying capping results in progress.

Progress Update, Week of March 20th, 2023

During the week of March 20, the Gowanus Remediation Team (GRT) continued the Demonstration Test for the RTA 1 Capping Operation. Capping material was placed and leveled.

Sealant was placed around the monopiles at the Union Street Bridge and at certain locations that were stabilized with In-Situ Stabilization (ISS).

Photos of construction activities are provided below.

Capping material placement in progress.
Placing sealant in ISS areas.

Progress Update, Week of March 27th, 2023

During the week of March 27th and following performance of the demonstration test for the RTA1 capping operation, the full scale capping began at target areas within RTA 1.

Sealant was placed at locations that were stabilized with In-Situ Stabilization (ISS).

Photos of construction activities are provided below.

Capping material placement in progress.
Placing sealant in ISS areas.

Progress Update, Week of April 3rd, 2023

During the week of April 3, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement continued and results were surveyed.

Photos of construction activities are provided below.

Capping material placement in progress.
Continued capping material placement in progress.

Progress Update, Week of April 10th, 2023

During the week of April 10, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement continued and results were surveyed.

This week the GRT began installing a specialized cap and ventilation system at the Carroll Street Bridge. Divers and equipment were mobilized. Sediment was graded in preparation for vent pipe installation.

Photos of construction activities are provided below.’

Capping material placement in progress.
Divers mobilizing at the Carroll Street Bridge.

Progress Update, Week of April 17th, 2023

During the week of April 17, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement continued north of Union Street.

Installation of the cap and ventilation system at the Carroll Street Bridge continued. Sediment was graded in preparation for vent pipe installation. Divers assisted with installing a vent pipe at the western abutment. Sealant was placed at the bridge’s fender.

Photos of construction activities are provided below.

Capping material placement in progress.
Vent pipe installed at the Carroll Street Bridge western abutment.

Progress Update, Week of April 24th, 2023

During the week of April 24, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed north of Union Street.

Installation continued for the cap and ventilation system at the Carroll Street Bridge. A vent pipe was installed at the eastern abutment.

Photos of construction activities are provided below.

Capping material placement in progress.
Vent pipe installation activities at the Carroll Street Bridge eastern abutment.

Progress Update, Week of May 1st, 2023

During the week of May 1, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed north of Union Street.

Installation continued for the cap and ventilation system at the Carroll Street Bridge. Sand was placed near the bridge.

Photos of construction activities are provided below.

Capping material placement in progress with low velocity spreader.
Sand placement at the Carroll Street Bridge near the newly installed ventilation system.

Progress Update, Week of May 8th, 2023

During the week of May 8, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material placement continued north of Union Street.

Installation continued for the cap and ventilation system at the Carroll Street Bridge. Completed work was inspected.

Photos of construction activities are provided below.

Capping material placement in progress north of Union Street.
Continued capping material placement in progress north of Union Street.

Progress Update, Week of May 15th, 2023

During the week of May 15, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material placement continued north of Union Street.

Installation continued for the cap and ventilation system at the Carroll Street Bridge. An installed vent pipe was adjusted to meet specifications. Completed work was surveyed. Sealant was placed over the cap.

Photos of construction activities are provided below.

Capping material placement in progress north of Union Street.
Sealant placement at the Carroll Street Bridge.