Progress Update, Week of May 22nd, 2023
During the week of May 22, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material placement continued north of Union Street.
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of May 22, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material placement continued north of Union Street.
During the week of May 15, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material placement continued north of Union Street.
During the week of May 8, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material placement continued north of Union Street.
During the week of May 1, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed north of Union Street.
During the week of April 24, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.