Progress Update, Week of November 1, 2021
During the week of November 1, the Gowanus Remediation Team (GRT) completed sediment removal at the Union Street Bridge.
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of November 1, the Gowanus Remediation Team (GRT) completed sediment removal at the Union Street Bridge.
During the week of October 25 the Gowanus Remediation Team (GRT) continued the demonstration of In Situ Stabilization (ISS).
During the week of October 18, the Gowanus Remediation Team (GRT) began a demonstration of In-Situ Stabilization (ISS).
During the week of October 11 the Gowanus Remediation Team continued removing sediment near the Union Street Bridge.
During the week of October 4 the Gowanus Remediation Team continued removing sediment near the Union Street Bridge.