Progress Update, Week of November 8, 2021
During the week of November 8, the Gowanus Remediation Team (GRT) continued mobilizing equipment and materials in preparation for sheet pile bulkhead installation work near the head of the canal.
During the week of November 8, the Gowanus Remediation Team (GRT) continued mobilizing equipment and materials in preparation for sheet pile bulkhead installation work near the head of the canal.
During the week of November 1, the Gowanus Remediation Team (GRT) completed sediment removal at the Union Street Bridge.
During the week of October 25 the Gowanus Remediation Team (GRT) continued the demonstration of In Situ Stabilization (ISS).
During the week of October 18, the Gowanus Remediation Team (GRT) began a demonstration of In-Situ Stabilization (ISS).
During the week of October 11 the Gowanus Remediation Team continued removing sediment near the Union Street Bridge.
This memorandum presents the findings of the archeologists review of sediments from a recovered floor safe that was identified in Memorandum 11, dated 4/13/21.
During the week of October 4 the Gowanus Remediation Team continued removing sediment near the Union Street Bridge.
During the week of September 27 the Gowanus Remediation Team continued removing sediment near the east side of the Union Street Bridge.
During the week of September 20 the Gowanus Remediation Team continued removing sediment near the east side of the Union Street Bridge.
During the week of September 13 the Gowanus Remediation Team continued removing sediment near the east side of the Union Street Bridge.