Progress Update, Week of November 22, 2021
During the week of November 22, the Gowanus Remediation Team continued sheet pile bulkhead installation work near the head of the canal.
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of November 22, the Gowanus Remediation Team continued sheet pile bulkhead installation work near the head of the canal.
During the week of November 15, the Gowanus Remediation Team began installing sheet pile bulkheads near the head of the canal.
During the week of November 8, the Gowanus Remediation Team (GRT) continued mobilizing equipment and materials in preparation for sheet pile bulkhead installation work near the head of the canal.
During the week of November 1, the Gowanus Remediation Team (GRT) completed sediment removal at the Union Street Bridge.
During the week of October 25 the Gowanus Remediation Team (GRT) continued the demonstration of In Situ Stabilization (ISS).