Progress Update, Week of July 3rd, 2023
During the week of July 3, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed south of Carroll Street.
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of July 3, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed south of Carroll Street.
During the week of June 26, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed south of Carroll Street.
During the week of June 19, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material was placed between Union Street and Carroll Street.
During the week of June 12, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material was placed between the headwall and Carroll Street.
During the week of June 5, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Material placement began between Union Street and Carroll Street.
To contact the Gowanus Remediation Team please email info@gowanussuperfund.com or call the hotline at (718) 569-5762.