Progress Update, Week of September 11th, 2023
During the week of September 11, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement was completed using the low velocity spreader barge.
Please scroll below to view the Gowanus Canal Superfund Project Team’s regular progress updates.
Also available on this page are past updates and special notices.
For additional information, please use the following links:
During the week of September 11, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material placement was completed using the low velocity spreader barge.
During the week of September 4, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed between Carroll Street and 3rd Street.
During the week of August 28, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed between Carroll Street and 3rd Street.
During the week of August 21, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation. Capping material was placed between Union Street and 3rd Street.
During the week of August 14, the Gowanus Remediation Team (GRT) continued the RTA 1 Capping Operation.
To contact the Gowanus Remediation Team please email info@gowanussuperfund.com or call the hotline at (718) 569-5762.