gowanus

Progress Update, Week of December 26th, 2022

  • by

During the week of December 26, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging near the Union Street Bridge and the Carroll Street Bridge abutments. Dredging also took place north of Union Street near the Flushing Tunnel.

Progress Update, Week of December 19th, 2022

  • by

During the week of December 19, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging near the Union Street Bridge and the Carroll Street Bridge abutments. Dredging also took place north of Union Street near the Flushing Tunnel. Divers were utilized for visual inspections.

Progress Update, Week of December 12th, 2022

  • by

During the week of December 12, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging near the Union Street Bridge and the Carroll Street Bridge abutments. Dredging also took place north of Union Street near the Flushing Tunnel.

Progress Update, Week of December 5th, 2022

  • by

During the week of December 5, the Gowanus Remediation Team (GRT) continued Phase 3 Dredging north of Union Street. Surveying was conducted to review dredging results.