Progress Update, Week of September 6, 2021
During the week of September 6 the Gowanus Remediation Team continued demobilizing the work barges at the Carroll Street Bridge.
During the week of September 6 the Gowanus Remediation Team continued demobilizing the work barges at the Carroll Street Bridge.
During the week of August 30 the Gowanus Remediation Team began demobilizing the pipe pile barge configuration at the Carroll Street bridge.
During the week of August 23 the Gowanus Remediation Team continued pipe pile operations at the Carroll Street bridge.
During the week of August 16 the Gowanus Remediation Team continued pipe pile operations at the Carroll Street bridge.
During the week of August 9 the Gowanus Remediation Team continued pipe pile installation along the canal-facing sides of the Carroll Street bridge abutments.
During the week of August 2 the Gowanus Remediation Team continued pipe pile installation along the canal-facing sides of the Carroll Street bridge abutments.
During the week of July 26 the Gowanus Remediation Team completed repositioning the work barges around the Carroll Street bridge.
Dredged material is processed according to the Level 1 Archaeological Monitoring protocol outlined in the draft Cultural Resource Monitoring Plan (revised September 2020).
During the week of July 19 the Gowanus Remediation Team continued repositioning the work barges around the Carroll Street bridge.
During the week of June 14 the Gowanus Remediation Team continued with ongoing pile driving operations.